2024 Initial Status:
As a result of delays during the 2023 construction season, some tasks were reserved for completion this year. These tasks include:
Full roadway closures are not anticipated, but there will be lane closures during the mill and overlay.
Project Description:
Brookings Municipal Utilities is installing a new 20"-diameter transmission watermain on 20th St S from 22nd Ave S to the water tower on Main Ave S. The gravity sewer on 20th St S from Medary Ave to Tanbury Lane will be upsized from 8" to 10". There will also be road resurfacing (mill and overlay).
Why the Project:
With the population of Brookings steadily rising, this watermain will help provide the water needed to support residents. It will connect to the upcoming new Water Treatment Plant.
Estimated Completion:
2024
Owner:
Engineer:
Contractor:
Winter Contracting, LLC
Copyright © 2024 Banner Associates, Inc. - All Rights Reserved.
Created and maintained by Banner Associates, Inc.
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.